Pattern review with the designer
A machined pattern sent to the landscape architect for sign-off on the cap radius and rope pitch before any moulding.
Worked example · Public realm bollards
Take a landscape architect who wants a mooring-post-inspired bollard with a rope relief band for a marina frontage. A split polyurethane mould with a silicone relief insert is designed to give a dense, well-compacted face suited to a coastal setting.
The brief

Take a marina regeneration with a bespoke mooring-post bollard. The design is a squat bollard shaped like a mooring post, with a rope-effect relief band below the cap. The run is large enough to justify proper tooling, and the precaster wants two matched moulds to keep pace with the programme.
The problem
The cap overhangs the shaft, which creates an undercut a one-piece rigid mould can't release. The rope band needed fine detail that polyurethane alone would soften over a long run.
The setting is coastal, so the designer wants a dense, well-compacted face with no blowholes on the relief where salt could get a foothold.

How we would approach it
A machined pattern sent to the landscape architect for sign-off on the cap radius and rope pitch before any moulding.
A two-part polyurethane body split along the back of the bollard, facing the kerb, so the line doesn't face the promenade.
The rope band cast as a silicone insert seated in the polyurethane, to keep the fine detail sharp across the run.
Vents at the cap underside and a vibration regime agreed with the precaster to keep the relief face dense.
Two identical moulds from the same pattern and material batch, labelled as a set.
The likely result
On a brief like this, the precaster would typically run both moulds in parallel through the programme, with the designer approving the first cast at the yard. We keep your masters and drawings on file so repeats are straightforward, including a matching replacement if a bollard is struck by a vehicle.
Lessons
On public realm pieces, ask early which face is seen and which faces the kerb or the wall. It's the single most useful fact for placing a split line.
Related
Get in touch
One photograph tells us what surface you're chasing, and one line about the mix tells us what silicone or polyurethane will survive it.
Real people, a real workshop
No call centre and no middlemen. When you contact TCI Construction, you speak to the team who design, build and check your mould.


Thomas LaneManaging Director
George PrestonDesign & Project Manager
Kelly BallingerHead of Partnerships
Jim AndertonProduction Manager
TheodoreEmployee Welfare